TM 9-2320-366-10-1
WARNING
Ensure there are at least two wraps of cable on hoist drum at all
times. Cable could come off hoist drum while load is being lifted.
Failure to comply may result in injury to personnel or damage to
equipment.
CAUTION
If circuit breaker trips while Light Material Handling Crane (LMHC) is
operating, allow 30 minutes to cool down. If load is suspended, reset circuit
breaker and lower load.
If circuit breaker trips again, notify Unit
Maintenance. Failure to comply may result in damage to equipment.
Do not jerk hoist control switch causing load to bounce. Failure to comply
may result in damage to equipment.
(4) Place hoist control switch (2) in down position to reel in cable (3) and lift load.
(5) Swing boom (1) to place load in desired location (para 2-29h).
(6) Place hoist control switch (2) in up position to lower load.
(7) Remove hook (4) from load.
2-267