TM 9-2320-366-10-1
Table 2-3. Preventive Maintenance Checks and Services (M1084 and M1086) (Cont)
Location
Item
No.
Interval
Item to
Check/
Service
Crewmember
Procedure
Not Fully
Mission Capable
If:
WARNING
Do not operate Material Handling Crane (MHC) unless outriggers are
set up and MHC is level from side to side. Failure to comply may
result in serious injury or death to personnel.
Keep boom clear of all electrical lines and other obstacles while
operating Material Handling Crane (MHC). Failure to comply may
result in serious injury or death to personnel.
NOTE
MHC will not operate if vehicle is not level or outriggers are not
extended to the ground.
2
During
MHC
Operation
(Cont)
h. Raise boom and mast
to operating position
(para 2-37d).
i.
Check that turntable
bearing retaining pin is
not missing or
damaged.
h. Lift and erec-
tion cylinders
do not raise
mast and
boom com-
pletely before
stopping.
2-134