g. Raise and Lower Load.
WARNING
Area must be clear of personnel before operating swing or telescoping
boom. Boom must be rotated and telescoped slowly enough so
Operator has control of load. If Operator cannot see load during
operation, operate Material Handling Crane (MHC) with REMOTE
CONTROL UNIT. Failure to comply may result in serious injury or
death to personnel or damage to equipment.
Attach guide lines to load to keep control of load at all times. Failure
to comply may result in serious injury or death to personnel or damage
to equipment.
(1) Refer to range diagram (para 2-37a) or to Table 2-14 to determine correct boom
angle.
(2) Position BOOM lever (1) to UP until boom angle indicator (2) shows correct reading.
2-371